Friday 2 January 2015

Progress by Photograph - January 2014 - January 2015


JANUARY 2014 - READY, STEADY, GO....ALL BUILDINGS STILL IN PLACE


























FEBRUARY 2014 - DEMOLITION IN PROGRESS 





















MARCH 2014 - SITE CLEAR - BASEMENT EXCAVATION IN PROGRESS
http://uwcsea-dover-high-school-project-blog.blogspot.com/2014/04/step-1-making-foundations-designing.html























APRIL /MAY 2014 - SITE CLEAR - BASEMENT EXCAVATION IN PROGRESS - START OF INSTALLATION OF ERSS 

























JUNE 2014 - CONSTRUCTION OF BASEMENT FOUNDATIONS (http://uwcsea-dover-high-school-project-blog.blogspot.com/2014/06/step-6-start-of-building-proper-casting.html)










JULY 2014 - FOUNDATIONS COMPLETE - CONSTRUCTION OF COLUMNS TO PREPARE FOR THE 2nd FLOOR (http://uwcsea-dover-high-school-project-blog.blogspot.com/2014/06/step-7-creating-columns.html)






AUGUST 2014 - Half of the 2nd floor cast, columns up to the 3rd floor.






1st SEPTEMBER - Half of 3rd floor cast - Connections to the Primary School block almost complete.








1st October






1st November









1st December












1st January - Happy New Year - 1 year since project start